Silver Spring Transit Center Costs Up 17.5%

Silver Spring Transit Center 2

The Washington Post reports that the costs of the Silver Spring Transit Center are up by $21 million, or 17.5%. Still no opening date scheduled for this highly complex transportation hub, which was discovered to be unsafe after it was built.

Councilmembers continue to blame the County Executive who blames the project designer, Parsons Brinckerhoff, and contractor, Foulger-Pratt. Nevertheless, Council President George Leventhal says councilmembers will “hold our noses and vote for” County Executive Leggett’s request.

Somehow, I don’t think it comforts anyone about the loss of another $21 million or the County’s management of the project that the Council President is holding his nose. While both the Executive and the Council promise that taxpayers won’t have to pay for the increase, it remains to be seen if all or a portion of the expense can be extracted from Parsons-Brinckerhoff and Foulger-Pratt.

Same Firm Involved in the Purple Line

Parsons-Brinckerhoff also estimated the ridership data for the Purple Line, a project George Leventhal supports. However, the firm still is hiding how it calculated ridership in response to public requests. (see here and here). In light of these past problems, this lack of transparency and the lack of demands for it by the State or the County is not encouraging.

Any unforeseen increases in costs for the Purple Line would not be born by the Parsons-Brinckerhoff or the federal government. Hopefully, the County will get the designer to pay for the cost increases in the Silver Spring Transit Center. Right now, however, County taxpayers are footing the bill with the money lost to other needed County infrastructure projects.

 

Share